ANALISA PERBANDINGAN PENGGUNAAN METODE BEKISTING SEMI SISTEM DENGAN PERI DARI SEGI WAKTU DAN BIAYA PADA PROYEK GEDUNG PAVILIUN RSSA “(Studi Kasus: Pembangunan Gedung Pelayanan Paviliun RSSA, Kota Malang, Jawa Timur)”

Mahrizal, Randy Ario (2024) ANALISA PERBANDINGAN PENGGUNAAN METODE BEKISTING SEMI SISTEM DENGAN PERI DARI SEGI WAKTU DAN BIAYA PADA PROYEK GEDUNG PAVILIUN RSSA “(Studi Kasus: Pembangunan Gedung Pelayanan Paviliun RSSA, Kota Malang, Jawa Timur)”. Undergraduate thesis, Universitas Muhammadiyah Malang.

[thumbnail of PENDAHULUAN.pdf]
Preview
Text
PENDAHULUAN.pdf

Download (697kB) | Preview
[thumbnail of BAB I.pdf]
Preview
Text
BAB I.pdf

Download (354kB) | Preview
[thumbnail of BAB II.pdf]
Preview
Text
BAB II.pdf

Download (712kB) | Preview
[thumbnail of BAB III.pdf]
Preview
Text
BAB III.pdf

Download (655kB) | Preview
[thumbnail of BAB IV.pdf] Text
BAB IV.pdf
Restricted to Registered users only

Download (1MB) | Request a copy
[thumbnail of BAB V.pdf] Text
BAB V.pdf
Restricted to Registered users only

Download (252kB) | Request a copy
[thumbnail of LAMPIRAN.pdf]
Preview
Text
LAMPIRAN.pdf

Download (1MB) | Preview

Abstract

Formwork work is a crucial stage in building construction, requiring careful analysis in terms of time and cost. This thesis focuses on comparing the use of two formwork methods, namely the semi-system formwork method and the PERI formwork method, in the construction project of the RSSA Pavilion Service Building in Malang City, East Java. This study aims to evaluate the efficiency of both methods in terms of execution duration and costs incurred. Cost analysis results show that the total cost of implementing the semi-system formwork structure work is Rp3,160,362,170.74, while the cost for the PERI formwork system method is Rp4,623,069,176.40. In this case, the PERI formwork system is 31.64% more expensive than the semi-system formwork method. Duration analysis results indicate that the total time for each formwork method is 99 days for the PERI formwork system method and 198 days for the semi-system method. Thus, the PERI formwork system method is 99 days faster than the semi-system formwork method. Based on the analysis results of the comparison of the two formwork methods in terms of cost and time, it is concluded that the effective formwork method to be used in the project depends on the project's priorities. If time is prioritized, the PERI formwork system method is more appropriate due to its shorter execution duration. However, if cost is prioritized, the semi-system formwork method is more suitable because it is cheaper than the PERI formwork system.

Item Type: Thesis (Undergraduate)
Student ID: 201710340311151
Keywords: Formwork, Semi System Method, PERI System, Cost and Time
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering > Department of Civil Engineering (22201)
Depositing User: 201710340311151 randy221298
Date Deposited: 14 Feb 2025 07:39
Last Modified: 14 Feb 2025 07:39
URI: https://eprints.umm.ac.id/id/eprint/15442

Actions (login required)

View Item
View Item