VERENNOLA, DAVERGO WILLY (2025) ANALISAPERCEPATAN PROYEK KONTRUKSI DENGAN MENGGUNAKAN METODE TIME COST TRADE OFF (TCTO) PADA PEMBANGUNAN GEDUNG FAKULTAS KEDOKTERAN GIGI UNIVERSITAS BRAWIJAYA MALANG (Studi Kasus : Pembangunan Gedung Fakultas Kedokteran Gigi Universitas Brawijaya Malang). Undergraduate thesis, Universitas Muhammadiyah Malang.
PENDAHULUAN.pdf
Download (3MB) | Preview
BAB 1.pdf
Download (77kB) | Preview
BAB 2.pdf
Download (418kB) | Preview
BAB 3.pdf
Restricted to Registered users only
Download (1MB) | Request a copy
BAB 4.pdf
Restricted to Registered users only
Download (597kB) | Request a copy
BAB 5.pdf
Restricted to Registered users only
Download (137kB) | Request a copy
lampiran.pdf
Restricted to Registered users only
Download (679kB) | Request a copy
POSTER.pdf
Restricted to Registered users only
Download (1MB) | Request a copy
Abstract
Construction management is a system for regulating construction activities that involves
various professional disciplines to achieve efficiency in cost, quality, and time. However,
construction projects often experience delays due to discrepancies between planned
schedules and actual field implementation. Factors contributing to delays include design
changes, project conditions, weather, equipment and material shortages, and labor
requirements. To address this issue, project duration acceleration methods such as fast
track, crash program, and time-cost trade-off (TCTO) are required.
This study analyzes the acceleration of the construction project for the Faculty of Dentistry
Building at Brawijaya University, Malang, carried out by PT. Santoso Shafanara Graha,
with a project value of IDR 23,665,334,000.00. The Time-Cost Trade-Off method is applied
using acceleration alternatives such as overtime work and additional labor. The objective
of this analysis is to determine the maximum acceleration duration with minimal additional
costs, ensuring the project is completed on time without causing losses to either the
contractor or the owner.
| Item Type: | Thesis (Undergraduate) |
|---|---|
| Student ID: | 201810340311265 |
| Keywords: | Construction management, project acceleration, delays, Time-Cost Trade-Off, building construction. |
| Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
| Divisions: | Faculty of Engineering > Department of Civil Engineering (22201) |
| Depositing User: | 201810340311265 davergowillyverennola |
| Date Deposited: | 21 May 2025 07:07 |
| Last Modified: | 21 May 2025 07:07 |
| URI: | https://eprints.umm.ac.id/id/eprint/17972 |